From 1.2 GW announced to about 824 MW in operation
March 18, 2025 Announced
Crusoe expands the Abilene campus to 1.2 GW.
Crusoe
September 10, 2026 Reported
Oracle reports 618 MW delivered across six of eight buildings.
Oracle earnings call, via Epoch AI
October 28, 2026 Reported
Oracle’s CFO says the site is nearing completion.
fDi Intelligence
November 1, 2026 Estimated
The last two buildings are estimated to be operational, adding 206 MW: about 824 MW of IT capacity.
Epoch AI
Most of that progress is reported by the companies themselves. Oracle had already reported 618 MW delivered across six of the eight buildings on September 10. Epoch AI then estimated that the final two buildings were operational by November 1, adding 206 MW to the September milestone.
Read the 824 MW with care
- The last step is an estimate. Epoch AI bases the final 206 MW on construction imagery and inferred fit-out timing, not on an operator announcement.
- It is IT capacity, not electricity drawn. 824 MW describes the estimated capacity of the IT equipment. How much power the campus actually draws would need metered data.
- It is not new demand. The 1.2 GW campus was announced in March 2025, so this news changes the pace of delivery, not the size of the plan. We add no megawatts to our view of planned demand.
Why it matters for CROSSOVER
Abilene is evidence of deployment pace. Buildings are going from structure to operation in months, and every building needs its power on the same timetable. Power that waits years for new turbines or transformers becomes the constraint on how fast capacity like this comes into service.
- Units sized to the building. CROSSOVER is designed in 20–24 MW-class units, so power can be added in step with each building rather than in one large plant.
- 800 V DC at the generator. No transformers, switchgear or separate rectifiers between the generator and the racks, which removes long-lead items from the schedule.
- A near-term timetable. CROSSOVER targets its first unit and data-center pilot in Q2 2028.
Read with care: Hyper Tech is not affiliated with OpenAI, Oracle, Crusoe, Epoch AI or fDi Intelligence, and is not involved in the Abilene project. Figures about Abilene are as published by the sources below. CROSSOVER is in development; ratings and dates are design targets.
Building AI capacity faster than the grid can follow?
Data-center developers and investors can see the technical package under a mutual NDA.
Request the NDASources
- fDi Intelligence: “OpenAI’s flagship Stargate mega campus nears the finish line”, November 2, 2026.
- Epoch AI: OpenAI Stargate Abilene, Frontier Data Centers hub, updated November 1, 2026.
- Crusoe: Crusoe expands AI data center campus in Abilene to 1.2 gigawatts, March 18, 2025.
- Hyper Tech: CROSSOVER.